Visitor Center Update
COMPLETE
Concrete slab is set
Slab edges cleaned and cleared for damp proofing
Concrete weir wall set at west end of bridge
NEXT UP
Steel delivery
Electric hook-up
Underground sanitary line from VC to septic tanks
Clearing and excavation for bridge abutments
Amphitheater foundation started
Stone at walking trail